5 1. **Clock source**: Set **NTP**.
6 1. **Server**: Set the server IP address or domain name.
7 1. **NTP synchronization test**: Check the time synchronization status.
8
9 Set **Active power control mode** to **Remote output control**.
10
11 [[image:1.png]]
12
13
14
15 [[image:2.png]]
16
17
18 * **Control area**: Set the areas for remote output control. To enable the function in some areas, the license needs to be imported and enabled.
19 * **Output control duration**: Set the time required for the inverter to change its output power from 0% to 100% or from 100% to 0%.
20 * **PV plant ID**: Set the ID assigned by the power company to the SmartLogger.
21 * **Remote output control server**: Set to curtailment.eniris.be
22 * If the connection between the SmartLogger and the server is abnormal, obtain the output control file in **.data** format from the website of the power company and import the file.
23 * After the SmartLogger connects to the server, you can export the relevant file.
24
25